Sanmu Solar Power Generation System Construction Project
Project data
- Customer Name
- Godogaisha Kaihatsu No. 31
- Company Address
- Kibara-otani 2293-1, Sanmu-shi, Chiba Prefecture
- Construction Name
- Sanmu Solar Power Generation System Construction Project
- Date of Completion
- August 2018
- No. of Instruments
- Electric power output: 1.0 MW (175 W x 6,272 panels)
- Project Name
- Sanmu Solar Power Generation System Construction Project
Construction of 1.0 MW mega solar power plant in Sanmu with good sunlight overlooking Kujukuri Beach in Chiba Prefecture
Renewable energy is increasing due to the introduction of the feed-in-tariff (FIT) system. A solar power plant--utilizing one form of renewable energy--was constructed on a 3.9 ha in Sanmu, Chiba Prefecture. Land development work for the project covered 72,000 m3.
Mountain forest trees 800 meters from Hyuga Station, which is a 40-minute train ride from JR Chiba Station on the Sobu Line, were logged to develop the land and install 6,272 solar panels. The generated power is transmitted by 6.6 kV high-voltage interconnect.
Residences and schools are situated around the site, and thus overtime work and work on holidays were completely restricted due to noise and for children's safety. Under the circumstances, trial operation was completed in August 2018, after which power transmission began.
Sanmu cedar logging
Sanmu cedar trees as tall as 25 to 30 meters were cut down and cut into a certain length on site before being carried out.
The cedar was processed into chips for fuel and sawdust for bedding of livestock animals at a processing plant.
Logged Sanmu cedar
Trees cut down with heavy machines
Logs carried out
Land development (cut earth and earth fill of 72,000 m3)
Although the land development work of the poorly-drained clay layer after the tree logging became more difficult due to unseasonal torrential rains and bomb cyclones, temporary reservoir construction and ground improvement work helped facilitate its completion.
【Aerial photos: Scenes from the land development work】
Solar panel installation (6,272 panels)
To make up for the delay with the land development work, piling, mount assembly, and solar panel installation work was conducted beginning in the northern area.
The work in the southern area was also conducted speedily in accordance with the progress of the land development work.
【The Scenes from the solar panel installation】
Electrical work, adjustments, and pre-use tests
A Power Conditioning System (PCS) consists of 50 kW x 20 units. Dielectric strength voltage tests were performed at night with no power generation.
The pre-use tests at full and partial loads were completed, and power transmission to the interconnect began on August 23.
【Scenes from the electrical work, adjustments, and pre-use tests】