Sanmu Solar Power Generation System Construction Project

Sanmu Solar Power Generation System Construction Project

Project data

Customer Name
Godogaisha Kaihatsu No. 31
Company Address
Kibara-otani 2293-1, Sanmu-shi, Chiba Prefecture
Construction Name
Sanmu Solar Power Generation System Construction Project
Date of Completion
August 2018
No. of Instruments
Electric power output: 1.0 MW (175 W x 6,272 panels)
Project Name
Sanmu Solar Power Generation System Construction Project

Construction of 1.0 MW mega solar power plant in Sanmu with good sunlight overlooking Kujukuri Beach in Chiba Prefecture

Renewable energy is increasing due to the introduction of the feed-in-tariff (FIT) system. A solar power plant--utilizing one form of renewable energy--was constructed on a 3.9 ha in Sanmu, Chiba Prefecture. Land development work for the project covered 72,000 m3.

Mountain forest trees 800 meters from Hyuga Station, which is a 40-minute train ride from JR Chiba Station on the Sobu Line, were logged to develop the land and install 6,272 solar panels. The generated power is transmitted by 6.6 kV high-voltage interconnect.

Residences and schools are situated around the site, and thus overtime work and work on holidays were completely restricted due to noise and for children's safety. Under the circumstances, trial operation was completed in August 2018, after which power transmission began.

Photo taken by drone
Solar power panels

Sanmu cedar logging

Sanmu cedar trees as tall as 25 to 30 meters were cut down and cut into a certain length on site before being carried out.

The cedar was processed into chips for fuel and sawdust for bedding of livestock animals at a processing plant.

DSCF0323.jpg

Logged Sanmu cedar

Trees cut down with heavy machines

DSC_4035.jpg

Logs carried out

Land development (cut earth and earth fill of 72,000 m3)

Although the land development work of the poorly-drained clay layer after the tree logging became more difficult due to unseasonal torrential rains and bomb cyclones, temporary reservoir construction and ground improvement work helped facilitate its completion.

【Aerial photos: Scenes from the land development work】

December 16
January 16
February 14
May 2
June 22
July 4

Solar panel installation (6,272 panels)

To make up for the delay with the land development work, piling, mount assembly, and solar panel installation work was conducted beginning in the northern area.

The work in the southern area was also conducted speedily in accordance with the progress of the land development work.

【The Scenes from the solar panel installation】

July 4 (1)
July 4 (2)
July 11
July 31
August 4
August 4

Electrical work, adjustments, and pre-use tests

A Power Conditioning System (PCS) consists of 50 kW x 20 units. Dielectric strength voltage tests were performed at night with no power generation.

The pre-use tests at full and partial loads were completed, and power transmission to the interconnect began on August 23.

【Scenes from the electrical work, adjustments, and pre-use tests】

June 27
July 11
July 18
July 25
August 10
August 16

BACK